Shin Yang secures RM316 million contract to finish two patrol vessels
The vessels were previously under THHE Destini, whose contract was terminated on Dec 31, 2024 following delays.

Shin Yang Group Bhd has secured a RM316 million contract to finish two delayed offshore patrol vessels for Malaysian Maritime Enforcement Agency (MMEA) use, according to its Bursa Malaysia filing. Wholly-owned subsidiary Shin Yang Shipyard Sdn Bhd will handle the outstanding work as rescue contractor.
Excluding sales tax, OPV 2 accounts for RM129.56 million of the contract and OPV 3 for RM186.44 million. The contract period begins on Oct 15, 2026 and ends on Oct 14, 2029. Completion is scheduled within 36 months for OPV 2 and within 30 months for OPV 3.
THHE Destini Sdn Bhd received the original RM740 million award in 2017 for three vessels, with delivery due in August 2020. The first, KM Tun Fatimah, was delivered in January 2024, but the other vessels remained delayed. THHE Destini's contract ended through termination on Dec 31, 2024.
The government subsequently approved RM200 million in additional funding to finish the two vessels, supplementing RM120 million remaining from the original allocation.
Shin Yang Group disclosed the proposed appointment on May 27, 2025, following a Home Ministry letter of intent dated May 20. That letter carried no legal commitment, and a final award depended on agreement over pricing, payment arrangements and other conditions.
The vessels are intended for prolonged border patrol missions, surveillance of the exclusive economic zone, and search-and-rescue duties. Contract acceptance requires an irrevocable performance bond amounting to RM5.27 million, alongside government training programme participation and industrial collaboration compliance.