Malakoff net profit slips 1.61%, expects fourth-quarter improvement
The power producer said Tanjung Bin Power had regained full generating capacity, following the return of Unit 30 to base-load operations on Aug 9.

Malakoff Corp Bhd reported RM27.76 million in net profit for 3QFY2026, down 1.61% from RM28.21 million a year earlier. The group expects fourth-quarter earnings to improve after a generating unit at Tanjung Bin Power Sdn Bhd (TBP) returned to service.
In its bourse filing, Malakoff attributed the earnings decline mainly to reduced contributions from TBP after a steam turbine generator rotor failure. The comparison also reflected a coal inventory net realisable value provision reversal in 3QFY2025. Increased associate contributions cushioned the decline.
Revenue for the quarter ended Sept 30, 2026 rose 33.82%, reaching RM2.26 billion against RM1.69 billion previously. Malakoff cited increased energy payments at TBP and Tanjung Bin Energy Sdn Bhd as applicable coal prices rose, alongside higher payments at Segari Energy Ventures Sdn Bhd on an increased despatch factor. It declared no quarterly dividend.
For the nine-month period, net profit dropped 36.35%, reaching RM79.58 million compared with RM125.03 million a year earlier. Revenue decreased 3.35%, coming in at RM5.55 billion against RM5.74 billion.
Malakoff said TBP regained full generating capacity when Unit 30 restarted base-load operations on Aug 9 following rotor installation. Group CEO Syahrunizam Samsudin said the earlier outage still weighed on quarterly profit, but the group entered the final quarter in a stronger position.
The group also said its GB3 plant in Lumut, Perak, restarted commercial operations in October, bringing back 429MW earlier than scheduled. Its Prai plant in Penang has operated since April.
Separately, Syahrunizam said a coal conveyor belt incident at the Tanjung Bin Complex had not interrupted operations at its two coal-fired plants, which have combined capacity of 3,100MW. Coal stocks remained sufficient, with remedial work expected to finish by the end of November.