Dialog discusses additional oil storage capacity at Pengerang
The group has land for another terminal with two million cubic metres of capacity, but tank construction approvals would take two to three years.

Dialog Group Bhd is discussing additional storage at Pengerang with oil producers looking to position Middle Eastern crude nearer Asian customers, executive chairman Tan Sri Dr Ngau Boon Keat said. Its existing facilities are full.
Speaking to reporters after the group’s annual general meeting, Ngau said Dialog had sufficient land in the Johor location for another terminal capable of holding two million cubic metres, equivalent to about 12.6 million barrels. Although land and deepwater jetties are available, obtaining approval to build tanks would take two to three years.
Ngau did not identify potential customers or disclose the capacity being discussed. He said producers could protect their ability to supply customers during disruptions to Middle Eastern exports by moving some crude to Asia during peacetime.
Dialog’s previously outlined investment plans for Pengerang Deepwater Terminals involve a further RM3 billion between 2027 and 2030. Those plans depend on demand from customers and commercial viability. Ngau said signed agreements backed about RM2 billion of that amount.
Much of the storage now being built is allocated to particular customers. The Pengerang Phase 3 expansion will provide 614,000 cubic metres for biofuels and refined petroleum products through a long-term arrangement with BP Singapore. Completion is scheduled for mid-2028.
Pengerang Terminals (Two) Sdn Bhd, a joint venture in which Dialog owns 25%, is separately adding 272,000 cubic metres for the Petronas–Enilive–Euglena biorefinery’s feedstocks and products. That project is covered by a 25-year take-or-pay agreement.
The two expansions are expected to lift operating storage capacity at Pengerang to almost five million cubic metres by 2028, compared with about four million cubic metres currently.