Binastra and client agree to end RM160 million construction contract

The group said RM23.82 million had been billed for work under the Damansara Perdana contract, with final settlement still subject to agreement.

Construction equipment and an unfinished building at a worksite
Photo: The Edge Malaysia

Binastra Corp Bhd and Dynamicz Sdn Bhd agreed on Nov 23 to end a RM160 million construction contract in Damansara Perdana, Selangor, following changes to the client’s plans for project implementation and procurement.

In a Bursa Malaysia filing, Binastra said its wholly owned subsidiary, Binastra Builders Sdn Bhd, had submitted progress billings totalling RM23.82 million to Dynamicz by the termination date.

Binastra said it did not expect a material impact on earnings, net assets or gearing. However, the unfinished portion of the contract would be removed from its order book.

Under the termination terms, Binastra Builders must stop work immediately and meet its remaining obligations in the termination letter. Dynamicz will arrange an assessment of completed work. The parties still need to agree on the final account before determining the final valuation, settling outstanding payments and releasing retention monies.

The group said neither side was admitting liability or default. Neither party could claim liquidated damages in connection with the mutual termination.

Awarded on Aug 2, 2024, the contract involved demolition and main building work for a development with 560 office units spread over four floors. Its scope also included a facilities floor, basement service areas, lifts and lift lobbies. Completion had originally been scheduled for July 30, 2026.

Binastra shares ended Nov 23 at RM2.40, down six sen or 2.44%, valuing the group at RM2.63 billion. The stock had gained more than 11% year-to-date.